Pavement Work Coming To Several Airmont Streets

By Idy Perl
Several streets in Airmont will be undergoing milling and
paving work over the next several weeks, starting this Tuesday, August 27. Portions
of the roads will be closed to traffic, with limited access for residents.
Drivers are cautioned to drive slowly after milling is completed since the roads might have raised manholes and the pavement will be uneven, which can cause damage to vehicles.
SHUART ROAD
Milling and Prepping: 8/27/24 - 8/30/24
Paving: 9/3/24 - 9/4/24
COBBLESTONE LANE
Milling and Prepping: 8/27/24 - 8/30/24
Paving: 9/3/24 - 9/4/24
SMITH HILL ROAD from CHURCH RD. to VAN GOGH LANE
Milling and Prepping: 9/5/24 - 9/6/24
Paving: 9/9/24 - 9/13/24 & 9/16/24 - 9/20/24
ACKERMAN AVENUE
Milling and Paving: 9/23/24 - 9/27/24
APPLELAND ROAD
Milling and Paving: 9/23/24 - 9/27/24
HIDDEN GLEN LANE
Milling and Paving: 9/30/24 - 10/4/24
Village of Airmont thanks all residents for their
cooperation while this construction is ongoing.