After Nearly Eight Months, Palisades Parkway Exit 9W Set to Reopen Monday Night
Yisroel R.
After nearly eight months of closure, the southbound Exit 9W ramp from the Palisades Interstate Parkway to the northbound New York State Thruway (I-87/I-287) in Clarkstown is scheduled to reopen Monday night, November 16, bringing relief to motorists who have been forced to use alternate routes for months.
The New York State Department of Transportation announced the reopening following an extended closure that began on March 25, 2026, as part of the ongoing Route 304 bridge rehabilitation project.
The ramp, which passes beneath the Route 304 overpass, has been closed to allow crews to carry out major structural repairs to the bridge. The work includes removing the existing bridge deck, replacing bridge pedestals and bearings, installing utilities, and making additional improvements.
The project has faced complications since construction began last year, after crews discovered structural problems that required more extensive repairs than originally anticipated.
The ramp was also closed for several months in 2025 before temporarily reopening ahead of the winter season. At the time, state officials explained that certain repairs could not safely or practically be completed during the colder months, requiring construction to resume in the spring.
As reported by Rockland Daily at that time, the ramp closed again on March 25, with the DOT warning that it would remain shut throughout the 2026 construction season.
Monday night’s scheduled reopening will mark the end of approximately 236 days of continuous closure, restoring an important connection between the Palisades Parkway and the northbound Thruway.